RECPDCL transfers the project SPV for the intra-state transmission system planned to evacuate power from the 3×800 MW STPP at Pirpainti.
NEW DELHI (India CSR): REC Power Development and Consultancy Limited (RECPDCL) has handed over Vikramshila Power Transmission Limited, the project-specific Special Purpose Vehicle (SPV) for an intra-state transmission project in Bihar, to Adani Energy Solutions Limited (AESL).
The transfer follows AESL’s selection as the successful bidder for the project titled “Evacuation of Power from 3×800 MW STPP Pirpainti.” The project is intended to develop the transmission infrastructure required to evacuate power from the Pirpainti Super Thermal Power Project and integrate it with Bihar’s intra-state grid.
RECPDCL is a wholly owned subsidiary of REC Limited, a Maharatna Central Public Sector Undertaking under the Ministry of Power. It acted as the Bid Process Coordinator for the project under the Tariff Based Competitive Bidding (TBCB) route.
Competitive Bidding Route
Adani Energy Solutions Limited emerged as the successful bidder through the TBCB process conducted by RECPDCL. The project will be developed on a Build, Own, Operate and Transfer (BOOT) basis, under which the successful developer will build and operate the transmission assets in accordance with the prescribed project framework.
The handover of the SPV represents a key implementation milestone, enabling the selected bidder to take forward the development of the proposed transmission network.
Ratnesh Kumar, General Manager (TBCB), RECPDCL, handed over Vikramshila Power Transmission Limited to Shashank Sharma, Chief Business Development Officer, Adani Energy Solutions Limited. The formal handover took place in the presence of officials from RECPDCL, AESL and Bihar State Power Transmission Company Limited (BSPTCL).
RECPDCL hands Vikramshila Power Transmission Ltd to Adani Energy Solutions for Bihar’s 3×800 MW Pirpainti power evacuation project.
Building Grid Capacity
The project broadly envisages the development of multiple gas-insulated substations and associated high-voltage transmission lines across Bihar.
The planned assets include a 400/220/132 kV gas-insulated grid substation at Jhanjharpur in Madhubani district; a 220/132/33 kV gas-insulated grid substation at Bethauli in Darbhanga district; a 400/220 kV gas-insulated grid substation at Begusarai; and a 220/33 kV gas-insulated Begusarai (New) grid substation.
In addition, the project will include associated 400 kV, 220 kV and 132 kV transmission lines. Together, these assets are designed to create the network capacity required for the evacuation and onward transmission of power from the Pirpainti generating station.
Enabling Energy Growth
Reliable transmission infrastructure is essential for bringing new electricity generation into the grid and moving power efficiently across regions. The proposed network is expected to strengthen Bihar’s transmission architecture and support the planned integration of generation capacity from Pirpainti.
For a growing state economy, transmission investments can support industrial activity, urban expansion, public services and wider energy access by ensuring that generation assets are connected to the grid through planned, high-capacity infrastructure.
The transaction also reflects the continued use of competitive bidding and SPV-based project development models in India’s power sector. Under this approach, RECPDCL coordinates the bidding process, while the successful developer takes forward project execution after the SPV transfer.
With the handover now completed, Adani Energy Solutions Limited will lead the next phase of developing the Vikramshila Power Transmission project, which is expected to play an important role in Bihar’s evolving electricity-transmission ecosystem.